The Choice Neighborhoods Implementation (CNI) Grant awarded to the Tulsa Housing Authority and the City of Tulsa will transform the Eugene Fields neighborhood into the thriving, vibrant River West community.

Grant Awarded – July 2018
1
Phases I & II Relocation – Q2 2019
2
Phases I & II Demolition – Q2/Q3 2019
3
4
Phases I & II Construction – Q1 2020
5
Phases I & II Reoccupancy and Leasing – Q3 2021
6
Phases III & IV Relocation – Q3 2020
7
Phases III & IV Construction – Q1 2021
8
Phase III Reoccupancy and Leasing – Q3 2022
Phase IV Reoccupancy and Leasing – Q4 2022
9
Phases V & VI Relocation – Q3 2021
10
Phases V & VI Construction – Q2 2022
11
12
Phase V Reoccupancy and Leasing – Q3 2023
13
Phase VI Reoccupancy and Leasing – Q4 2023

News

Construction Begins at Choice Neighborhoods Tulsa Site, Marking Next Step in Historic Project

Construction for the historic Choice Neighborhoods Implementation (CNI) Tulsa project has begun at Riverview Park Apartments. Phase one construction encompasses 74 housing units, including 37 […]